Energy Projects Near You

Rassau Industrial Estate, Rassau (8 MW battery storage)

Rassau Industrial Estate, Rassau is an 8 MW battery storage project in Blaenau Gwent, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 July 2023, not yet built; the record was last updated on 18 September 2023. REPD also records that the planning permission expired on 24 July 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWbattery storage
approved, not builtmay be out of datestatus in REPD
18 September 2023record last updated
Blaenau Gwentcouncil area

REPD also records that the planning permission expired on 24 July 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
28 March 2023Application submitted
24 July 2023Planning permission granted
24 July 2026Permission expired

Project details

Technology
battery storage (co-located with re)
Capacity
8 MW
Status (REPD)
approved, not built
Record last updated
18 September 2023
Operator or applicant
Private Developer
Planning authority
Blaenau Gwent
Planning application reference
C/2023/0078
Address (REPD)
Rassau Industrial Estate, Adj To Generating Plant, Rassau, Ebbw Vale
Council area (by location)
Blaenau Gwent
Time to decision
17 weeks
Name in REPD
Rassau Industrial Estate, Rassau - Battery Energy Storage
REPD reference
13708

The scheme also includes rooftop solar, recorded separately in REPD (approved, not built).

Who decides

ApplicationsBlaenau GwentUK
Decided applications (solar, wind, battery)1010,236
Refused2 (20%)19%
Solar refused0 of 412%
Onshore wind refused2 of 345%
Battery storage refused0 of 316%
Median time from submission to decision16.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rassau Industrial Estatebattery storage6under construction0.2
Manmoel Wind Farmwind farm28approved, not built5.7
Wauntysswg Farm, near Tredagarsolar farm30approved, not built5.8
Convatec Green Manufacturing Hubwind farm15refused6.0
Convatec Green Manufacturing Hubsolar farm5refused6.0
Mynydd James Wind Farmwind farm31.2application withdrawn6.7
Pen March Wind Farmwind farm30refused7.1
Merthyr Commonwind farm24.3refused7.6
Pendragon Fach Wind Farmwind farm5.2refused on appeal7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8019, -3.2358).