Solar, wind and battery projects near Ebbw Vale (NP23)
30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NP23 (Blaenau Gwent): 2 are waiting for a planning decision, 13 approved but not yet running, 4 operational. The largest live scheme is Mynydd Carn Wind Farm (34 MW wind farm, approved on 11 March 2024, not yet built), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NP23
Projects of 1 MW and more (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Rassau Industrial Estatewind turbine | wind turbine | 1.5 | approved, not built may be out of dateupdated Sep 2019 | Oct 2018 | granted Jul 2019 | Sep 2019 | Blaenau Gwent | 3.0 |
| Rassau Industrial Estatebattery storage | battery storage | 6 | under constructionupdated Jan 2022 | Nov 2019 | granted Jan 2020 | Jan 2022 | Blaenau Gwent | 3.2 |
| Rassau Industrial Estate, Rassaubattery storage | battery storage | 8 | approved, not built may be out of dateupdated Sep 2023 | Mar 2023 | granted Jul 2023 | Sep 2023 | Blaenau Gwent | 3.2 |
| Mynydd James Wind Farmwind farm | wind farm | 31.2 | application withdrawnupdated Oct 2005 | Jul 2006 | — | Oct 2005 | Blaenau Gwent | 3.6 |
| Manmoel Wind Farmwind farm | wind farm | 28 | approved, not builtupdated Mar 2026 | Aug 2023 | granted Oct 2024 | Mar 2026 | Blaenau Gwent | 3.6 |
| Pendragon Fach Wind Farmwind farm | wind farm | 5.2 | refused on appealupdated Jan 2012 | Jun 2006 | refused Apr 2010 | Jan 2012 | Blaenau Gwent | 4.7 |
| Wauntysswg Farm, near Tredagarsolar farm | solar farm | 30 | approved, not built may be out of dateupdated Sep 2020 | Jul 2018 | granted Aug 2019 | Sep 2020 | Blaenau Gwent | 5.2 |
| Pen Bryn Oer Wind Farmwind farm | wind farm | 4 | operationalupdated May 2018 | Jun 2013 | granted Aug 2015 | May 2018 | Caerphilly | 5.5 |
| Mynydd Carn Wind Farmwind farm | wind farm | 34 | approved, not builtupdated Feb 2026 | Nov 2022 | granted Mar 2024 | Feb 2026 | Blaenau Gwent | 6.4 |
| Hafod-y-Dafalwind farm | wind farm | 4 | refused on appealupdated Oct 2015 | Oct 2013 | refused Jul 2014 | Oct 2015 | Blaenau Gwent | 6.7 |
| Hafod-Y-Dafal Farmsolar farm | solar farm | 14 | operationalupdated Jan 2016 | May 2014 | granted Nov 2014 | Jan 2016 | Blaenau Gwent | 7.2 |
| Convatec Green Manufacturing Hubwind farm | wind farm | 15 | refusedupdated Jan 2026 | Apr 2025 | refused Nov 2025 | Jan 2026 | Caerphilly | 7.2 |
| Convatec Green Manufacturing Hubsolar farm | solar farm | 5 | refusedupdated Jan 2026 | Apr 2025 | refused Nov 2025 | Jan 2026 | Caerphilly | 7.2 |
| Arail Farm Roadsolar farm | solar farm | 5 | application withdrawnupdated Apr 2016 | Sep 2015 | — | Apr 2016 | Blaenau Gwent | 8.1 |
| Biffa Waste Services, Fochriw Roadbattery storage | battery storage | 2 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Caerphilly | 8.7 |
| Manmoel Road Solar Parksolar farm | solar farm | 4.1 | operationalupdated Dec 2017 | Jun 2015 | granted Nov 2015 | Dec 2017 | Caerphilly | 9.2 |
| Pen March Wind Farmwind farm | wind farm | 30 | refusedupdated May 2025 | Oct 2023 | refused Mar 2025 | May 2025 | Merthyr Tydfil | 9.3 |
| Land At Cwm Bargoedsolar farm | solar farm | 5 | operationalupdated Mar 2017 | Jun 2015 | granted Sep 2015 | Mar 2017 | Caerphilly | 9.3 |
| Cwmbargoed Disposal Pointwind turbine | wind turbine | 1.5 | refused on appealupdated Jan 2018 | Jan 2017 | refused Mar 2017 | Jan 2018 | Caerphilly | 9.5 |
| Fochriw Windwind farm | wind farm | 1.7 | application withdrawnupdated Nov 2012 | Dec 2005 | — | Nov 2012 | Caerphilly | 9.5 |
| Merthyr Commonwind farm | wind farm | 24.3 | refusedupdated Oct 2013 | Aug 2004 | refused Nov 2005 | Oct 2013 | Merthyr Tydfil | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Rassau Industrial Estate, Unit 19wind turbine | wind turbine | — | application submitted may be out of dateupdated Jan 2021 | Dec 2020 | — | Jan 2021 | Blaenau Gwent | 3.1 |
| Rassau Industrial Estate, Rassaurooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Sep 2023 | Mar 2023 | granted Jul 2023 | Sep 2023 | Blaenau Gwent | 3.2 |
| Roseheyworth Business Park Solar Array & Battery Storagesolar farm | solar farm | — | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Blaenau Gwent | 5.6 |
| Roseheyworth Business Park Solar Array & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Blaenau Gwent | 5.6 |
| Tafarnaubach Industrial Estaterooftop solar | rooftop solar | 0.9 | approved, not built may be out of dateupdated Aug 2020 | Mar 2019 | granted Apr 2019 | Aug 2020 | Caerphilly | 6.0 |
| Duffryn View, Rhymney - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Caerphilly | 6.6 |
| Pen-Yr-Heol Farm, Hollybushwind turbine | wind turbine | — | approved, not built may be out of dateupdated Feb 2022 | Feb 2021 | granted May 2021 | Feb 2022 | Caerphilly | 7.3 |
| Pengarnddu Industrial Estate, Dowlaisbattery storage | battery storage | — | abandonedupdated Dec 2021 | Dec 2021 | — | Dec 2021 | Merthyr Tydfil | 9.5 |
| Unit E, Dowlais Top Retail Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Jan 2026 | granted Feb 2026 | Mar 2026 | Merthyr Tydfil | 9.8 |
Distance from the average position of the NP23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 0 | 2 | 3 | 1 | 30 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 1.1 |
| Wind farm | 10 | 0 | 2 | 1 | 5 | 62 |
| Wind turbine | 4 | 1 | 2 | 0 | 1 | 1.5 |
| Battery storage | 6 | 1 | 4 | 0 | 0 | 16.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Blaenau Gwent decides solar, wind and battery applications
| Applications | Blaenau Gwent | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 10 | 10,236 |
| Refused | 2 (20%) | 19% |
| Solar refused | 0 of 4 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 16.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NP23, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.