Energy Projects Near You

Wauntysswg Farm, near Tredagar (30 MW solar farm)

Wauntysswg Farm, near Tredagar is a 30 MW solar farm project in Blaenau Gwent, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 1 August 2019, not yet built; the record was last updated on 24 September 2020. It is decided by the Welsh Government as a development of national significance. REPD also records that the planning permission expired on 31 July 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtmay be out of datestatus in REPD
24 September 2020record last updated
Blaenau Gwentcouncil area

REPD also records that the planning permission expired on 31 July 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
28 July 2018Application submitted
1 August 2019Planning permission granted
31 July 2024Permission expired

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
24 September 2020
Operator or applicant
Elgin Energy
Planning authority
Welsh Government (NSIP)
Planning application reference
DNS/3213639
Address (REPD)
Wauntysswg Farm, Abertysswg, Rhymney, Tredegar
Council area (by location)
Blaenau Gwent
Time to decision
53 weeks
REPD reference
6477

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Manmoel Wind Farmwind farm28approved, not built2.6
Convatec Green Manufacturing Hubwind farm15refused3.7
Convatec Green Manufacturing Hubsolar farm5refused3.7
Land At Cwm Bargoedsolar farm5operational4.9
Gelligaer 'B' Wind Farmwind farm9.8application withdrawn5.0
Gelligaer 'A' Wind Farmwind farm9.8application withdrawn5.0
Bedlinog Wind Farmwind farm6application withdrawn5.6
Rassau Industrial Estate, Rassaubattery storage8approved, not built5.8
Rassau Industrial Estatebattery storage6under construction6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7501, -3.2461).