Solar, wind and battery projects near Bargoed (CF81)
40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CF81 (Caerphilly): 6 are waiting for a planning decision, 9 approved but not yet running, 11 operational. The largest live scheme is National Road, Cilfynydd (200 MW battery storage, application submitted on 16 June 2025, no decision recorded), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CF81
Projects of 1 MW and more (32)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hendai Farmsolar farm | solar farm | 13.4 | operationalupdated Mar 2015 | Dec 2013 | granted Apr 2014 | Mar 2015 | Caerphilly | 3.8 |
| Bedlinog Wind Farmwind farm | wind farm | 6 | application withdrawnupdated Sep 2013 | Sep 2011 | — | Sep 2013 | Merthyr Tydfil | 4.0 |
| Manmoel Road Solar Parksolar farm | solar farm | 4.1 | operationalupdated Dec 2017 | Jun 2015 | granted Nov 2015 | Dec 2017 | Caerphilly | 4.5 |
| Land at Darran Farmsolar farm | solar farm | 2.6 | operationalupdated Oct 2017 | Oct 2014 | granted Mar 2016 | Oct 2017 | Caerphilly | 4.7 |
| Gelligaer 'A' Wind Farmwind farm | wind farm | 9.8 | application withdrawnupdated Jun 2002 | Aug 1999 | — | Jun 2002 | Caerphilly | 4.7 |
| Gelligaer 'B' Wind Farmwind farm | wind farm | 9.8 | application withdrawnupdated Jun 2002 | — | — | Jun 2002 | Caerphilly | 4.7 |
| Tir Nyth Soalr Parksolar farm | solar farm | 5 | refusedupdated May 2016 | Jul 2015 | refused Mar 2016 | May 2016 | Merthyr Tydfil | 5.2 |
| Fochriw Windwind farm | wind farm | 1.7 | application withdrawnupdated Nov 2012 | Dec 2005 | — | Nov 2012 | Caerphilly | 5.3 |
| Wauntysswg Farm, near Tredagarsolar farm | solar farm | 30 | approved, not built may be out of dateupdated Sep 2020 | Jul 2018 | granted Aug 2019 | Sep 2020 | Blaenau Gwent | 5.3 |
| Oakdale Business Parkwind farm | wind farm | 4 | operationalupdated Mar 2014 | Jul 2011 | granted Oct 2011 | Mar 2014 | Caerphilly | 5.3 |
| Land At Pen Y Fanwind turbine | wind turbine | 1.5 | application withdrawnupdated Aug 2015 | Jun 2015 | — | Aug 2015 | Caerphilly | 5.8 |
| Pen-Y-Fan Industrial Estatewind turbine | wind turbine | 1.8 | refusedupdated Oct 2018 | Oct 2017 | refused Sep 2018 | Oct 2018 | Caerphilly | 5.9 |
| Manmoel Wind Farmwind farm | wind farm | 28 | approved, not builtupdated Mar 2026 | Aug 2023 | granted Oct 2024 | Mar 2026 | Blaenau Gwent | 6.2 |
| Hafod-y-Dafalwind farm | wind farm | 4 | refused on appealupdated Oct 2015 | Oct 2013 | refused Jul 2014 | Oct 2015 | Blaenau Gwent | 6.5 |
| Hafod-Y-Dafal Farmsolar farm | solar farm | 14 | operationalupdated Jan 2016 | May 2014 | granted Nov 2014 | Jan 2016 | Blaenau Gwent | 6.5 |
| Mynydd Llanhilleth Wind Farmwind farm | wind farm | 34 | application submittedupdated Sep 2025 | May 2025 | — | Sep 2025 | Caerphilly | 6.6 |
| Land At Cwm Bargoedsolar farm | solar farm | 5 | operationalupdated Mar 2017 | Jun 2015 | granted Sep 2015 | Mar 2017 | Caerphilly | 7.0 |
| Upper Pant-Ysgawen Farm, Maes-Yr-Haf Lanebattery storage | battery storage | 28 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Caerphilly | 7.1 |
| Upper Pant-Ysgawen Farm/Crumlinsolar farm | solar farm | 4.9 | operationalupdated Apr 2017 | Jul 2015 | granted Sep 2015 | Apr 2017 | Caerphilly | 7.2 |
| Cwmbargoed Disposal Pointwind turbine | wind turbine | 1.5 | refused on appealupdated Jan 2018 | Jan 2017 | refused Mar 2017 | Jan 2018 | Caerphilly | 7.2 |
| Mynydd Carn Wind Farmwind farm | wind farm | 34 | approved, not builtupdated Feb 2026 | Nov 2022 | granted Mar 2024 | Feb 2026 | Blaenau Gwent | 7.5 |
| Trecelyn Wind Farmwind farm | wind farm | 20 | application submitted may be out of dateupdated May 2025 | Jun 2024 | — | May 2025 | Caerphilly | 7.6 |
| Convatec Green Manufacturing Hubwind farm | wind farm | 15 | refusedupdated Jan 2026 | Apr 2025 | refused Nov 2025 | Jan 2026 | Caerphilly | 7.6 |
| Convatec Green Manufacturing Hubsolar farm | solar farm | 5 | refusedupdated Jan 2026 | Apr 2025 | refused Nov 2025 | Jan 2026 | Caerphilly | 7.6 |
| Arail Farm Roadsolar farm | solar farm | 5 | application withdrawnupdated Apr 2016 | Sep 2015 | — | Apr 2016 | Blaenau Gwent | 7.6 |
| Pen Bryn Oer Wind Farmwind farm | wind farm | 4 | operationalupdated May 2018 | Jun 2013 | granted Aug 2015 | May 2018 | Caerphilly | 8.4 |
| Biffa Waste Services, Fochriw Roadbattery storage | battery storage | 2 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Caerphilly | 9.0 |
| Cwmcaesingrug Farmsolar farm | solar farm | 10 | operationalupdated Sep 2015 | May 2014 | granted Aug 2014 | Sep 2015 | Caerphilly | 9.1 |
| Penrhiwarwydd Farmsolar farm | solar farm | 8.5 | operationalupdated Apr 2015 | Jul 2014 | granted Nov 2014 | Apr 2015 | Caerphilly | 9.8 |
| National Road, Cilfynyddbattery storage | battery storage | 200 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | Rhondda Cynon Taf | 9.8 |
| Pen Rhiw Caradogsolar farm | solar farm | 4.7 | operationalupdated May 2017 | Sep 2013 | granted Jul 2016 | May 2017 | Rhondda Cynon Taf | 10.0 |
| Penyrheol Las Farmwind farm | wind farm | 1 | refused on appealupdated Mar 2018 | Mar 2017 | refused May 2017 | Mar 2018 | Caerphilly | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Pen-Yr-Heol Farm, Hollybushwind turbine | wind turbine | — | approved, not built may be out of dateupdated Feb 2022 | Feb 2021 | granted May 2021 | Feb 2022 | Caerphilly | 2.5 |
| Duffryn View, Rhymney - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Caerphilly | 6.5 |
| Roseheyworth Business Park Solar Array & Battery Storagesolar farm | solar farm | — | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Blaenau Gwent | 7.8 |
| Roseheyworth Business Park Solar Array & Battery Storagebattery storage | battery storage | — | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Blaenau Gwent | 7.8 |
| Herbert Street, Hafodyrynys - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 | Caerphilly | 9.0 |
| Tafarnaubach Industrial Estaterooftop solar | rooftop solar | 0.9 | approved, not built may be out of dateupdated Aug 2020 | Mar 2019 | granted Apr 2019 | Aug 2020 | Caerphilly | 9.5 |
| Pengarnddu Industrial Estate, Dowlaisbattery storage | battery storage | — | abandonedupdated Dec 2021 | Dec 2021 | — | Dec 2021 | Merthyr Tydfil | 9.7 |
| Unit E, Dowlais Top Retail Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Jan 2026 | granted Feb 2026 | Mar 2026 | Merthyr Tydfil | 9.8 |
Distance from the average position of the CF81 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 0 | 2 | 9 | 2 | 30 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 1.1 |
| Wind farm | 13 | 2 | 2 | 2 | 3 | 116 |
| Wind turbine | 4 | 0 | 1 | 0 | 2 | 0 |
| Battery storage | 7 | 4 | 2 | 0 | 0 | 230 |
MW in pipeline: pending, approved and under-construction capacity.
How Caerphilly decides solar, wind and battery applications
| Applications | Caerphilly | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 14 | 10,236 |
| Refused | 4 (29%) | 19% |
| Solar refused | 0 of 7 | 12% |
| Onshore wind refused | 4 of 6 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 14.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CF81, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.