Energy Projects Near You

Ogmore & Garw (12 MW wind farm)

Ogmore & Garw is a 12 MW wind farm project in Bridgend, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 13 March 2002; the record was last updated on 8 October 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWwind farm
refusedstatus in REPD
8 October 2013record last updated
Bridgendcouncil area

Planning timeline

DateStage
28 September 2001Application submitted
13 March 2002Refused by the planning authority

Project details

Technology
wind farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
8 October 2013
Operator or applicant
AMEC
Planning authority
Bridgend
Planning application reference
P/01/887
Address (REPD)
Nant Y Moel, Bridgend, Mid Glamorgan
Council area (by location)
Bridgend
Time to decision
24 weeks
REPD reference
2631

Who decides

ApplicationsBridgendUK
Decided applications (solar, wind, battery)1910,236
Refused7 (37%)19%
Solar refused1 of 812%
Onshore wind refused6 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision23.7 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Werfa Wind Farmwind farm14.3refused0.6
Werfawind farm47.5refused on appeal0.9
Upper Ogmore Wind Farmwind farm25.2approved, not built2.0
Llynfi Afan Renewable Energy Parkwind farm6operational3.1
Llynfi Renewable Energy Park, Land at Mynydd Caerauwind farm24operational3.5
Pant y Wal (Extension)wind farm5approved, not built4.4
Pant y walwind farm25operational5.4
Foel Fawrsolar farm5.1permission expired5.8
Wind Turbines at Mynydd Y Glyn Wind Farmwind farm30approved, not built5.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6388, -3.5707).