Pant y wal (25 MW wind farm)

Pant y wal is a 25 MW wind farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2013; the record was last updated on 3 June 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWwind farm
operationalstatus in REPD
3 June 2013record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
31 March 2006Application submitted
26 April 2006Refused by the planning authority
4 May 2011Planning permission granted
4 May 2011Appeal allowed
1 April 2012Construction started
1 June 2013Operational

Project details

Technology
wind farm
Capacity
25 MW
Status (REPD)
operational
Record last updated
3 June 2013
Operator or applicant
Pennant Wind Energy Ventures (PWEV)
Planning authority
Bridgend
Planning application reference
P/06/417/FUL
Turbines
10
Turbine height
115 m
Address (REPD)
Mynydd Maesteg, Mynydd Pwlle yr Helog, Ogmore Vale, Rhondda Valley
Council area (by location)
Rhondda Cynon Taf
Time to decision
266 weeks
REPD reference
4039

Who decides

ApplicationsBridgendUK
Decided applications (solar, wind, battery)1910,236
Refused7 (37%)19%
Solar refused1 of 812%
Onshore wind refused6 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision23.7 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fforch Nest Wind Farm pt1wind farm10operational0.7
Fforch Nest Wind Farmwind farm16abandoned0.7
Fforch Nest Wind Farm pt2wind farm17.5operational0.9
Pant y Wal (Extension)wind farm5approved, not built1.9
Mynydd Pen-y-Graig Wind Farmwind farm15application withdrawn2.9
Pant y wal extensionwind farm20operational3.1
Upper Ogmore Wind Farmwind farm25.2approved, not built3.4
Trane Renewable Energy Parkwind farm11.9application withdrawn3.5
Wind Turbines at Mynydd Y Glyn Wind Farmwind farm30approved, not built4.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6129, -3.505).