Solar, wind and battery projects near Porth (CF39)
44 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CF39 (Rhondda Cynon Taf): 11 are waiting for a planning decision, 13 approved but not yet running, 14 operational. The largest live scheme is National Road, Cilfynydd (200 MW battery storage, application submitted on 16 June 2025, no decision recorded), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CF39
Projects of 1 MW and more (39)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Trane Renewable Energy Parkwind farm | wind farm | 11.9 | application withdrawnupdated Jun 2010 | — | — | Jun 2010 | Rhondda Cynon Taf | 2.6 |
| Mynydd Pen-y-Graig Wind Farmwind farm | wind farm | 15 | application withdrawnupdated Sep 2016 | Jun 2015 | — | Sep 2016 | Rhondda Cynon Taf | 2.8 |
| Rhondda Valley Solar Farmsolar farm | solar farm | 4.8 | application withdrawnupdated Dec 2014 | Mar 2011 | — | Dec 2014 | Rhondda Cynon Taf | 3.6 |
| Coed Ely Solar Farmsolar farm | solar farm | 6 | under constructionupdated Apr 2025 | Sep 2023 | granted Dec 2023 | Apr 2025 | Rhondda Cynon Taf | 3.6 |
| Llwyncelyn Wind Farmwind farm | wind farm | 7.2 | application submitted may be out of dateupdated Oct 2018 | Aug 2018 | — | Oct 2018 | Rhondda Cynon Taf | 3.7 |
| Taff Ely Wind Farmwind farm | wind farm | 9 | operationalupdated Jun 2011 | — | — | Jun 2011 | Rhondda Cynon Taf | 4.3 |
| Graig Fatha Farmwind turbine | wind turbine | 2.5 | operationalupdated Mar 2023 | May 2017 | granted Jun 2017 | Mar 2023 | Rhondda Cynon Taf | 4.5 |
| Mynydd Portref Wind Farm extensionwind farm | wind farm | 12 | operationalupdated Apr 2017 | Jun 2012 | granted Dec 2014 | Apr 2017 | Rhondda Cynon Taf | 4.6 |
| Headwind Taff Ely Wind Farm (Repowering)wind farm | wind farm | 17.5 | permission expiredupdated Feb 2020 | Dec 2011 | granted Apr 2013 | Feb 2020 | Rhondda Cynon Taf | 4.8 |
| Fforch Nest Wind Farm pt2wind farm | wind farm | 17.5 | operationalupdated Jun 2013 | Mar 2006 | granted May 2011 | Jun 2013 | Rhondda Cynon Taf | 4.9 |
| Fforch Nest Wind Farmwind farm | wind farm | 16 | abandonedupdated Feb 2013 | Aug 2006 | granted Aug 2009 | Feb 2013 | Rhondda Cynon Taf | 4.9 |
| Fforch Nest Wind Farm pt1wind farm | wind farm | 10 | operationalupdated Jun 2013 | Aug 2006 | granted May 2011 | Jun 2013 | Rhondda Cynon Taf | 4.9 |
| Malthouse Farmwind turbine | wind turbine | 1.5 | application withdrawnupdated Dec 2015 | Jul 2014 | — | Dec 2015 | Rhondda Cynon Taf | 5.1 |
| West of Rhiwfelin Fach Farmwind turbine | wind turbine | 1.5 | operationalupdated Sep 2018 | Feb 2016 | granted Jul 2016 | Sep 2018 | Rhondda Cynon Taf | 5.1 |
| Former Nant-y-Gwyddon Landfill Sitewind turbine | wind turbine | 1.5 | under constructionupdated Aug 2023 | Mar 2017 | granted Aug 2017 | Aug 2023 | Rhondda Cynon Taf | 5.3 |
| Mynydd Portrefwind farm | wind farm | 9.4 | operationalupdated Jun 2018 | Jun 2006 | granted Jul 2008 | Jun 2018 | Rhondda Cynon Taf | 5.3 |
| Dyffryn Farm, Ynysmaerdysolar farm | solar farm | 9.9 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | Rhondda Cynon Taf | 5.4 |
| Energy Centre Royal Mintbattery storage | battery storage | 20 | operationalupdated Aug 2023 | Sep 2019 | granted Jan 2020 | Aug 2023 | Rhondda Cynon Taf | 5.5 |
| Talbot Green, Llantrisant Solar Farmsolar farm | solar farm | 9.9 | approved, not builtupdated Feb 2026 | Dec 2022 | granted Apr 2024 | Feb 2026 | Rhondda Cynon Taf | 5.6 |
| Pant y walwind farm | wind farm | 25 | operationalupdated Jun 2013 | Mar 2006 | granted May 2011 | Jun 2013 | Rhondda Cynon Taf | 5.7 |
| Llanwonno Wind Farmsolar farm | solar farm | 30.7 | application submittedupdated Apr 2025 | Mar 2025 | — | Apr 2025 | Rhondda Cynon Taf | 5.8 |
| Llanwonno Wind Farmwind farm | wind farm | 30.4 | application submittedupdated Apr 2025 | Mar 2025 | — | Apr 2025 | Rhondda Cynon Taf | 5.8 |
| Llanwonno Wind Farmbattery storage | battery storage | 30 | application submittedupdated Apr 2025 | Mar 2025 | — | Apr 2025 | Rhondda Cynon Taf | 5.8 |
| Penrhys Wind Farm/Ferndale Power Factorywind farm | wind farm | 6.4 | operationalupdated Nov 2013 | Feb 2003 | granted Mar 2005 | Nov 2013 | Rhondda Cynon Taf | 6.0 |
| Berthlwyd Farmsolar farm | solar farm | 5 | operationalupdated Dec 2017 | Jun 2015 | granted Mar 2016 | Dec 2017 | Rhondda Cynon Taf | 6.7 |
| Pant y wal extensionwind farm | wind farm | 20 | operationalupdated Aug 2017 | Apr 2014 | granted Apr 2015 | Aug 2017 | Bridgend | 6.8 |
| Wind Turbines at Mynydd Y Glyn Wind Farmwind farm | wind farm | 30 | approved, not builtupdated Jan 2026 | May 2023 | granted Jun 2024 | Jan 2026 | Rhondda Cynon Taf | 6.8 |
| Hendir Uchaf Farm, Minffrwd Roadsolar farm | solar farm | 1.5 | application submittedupdated Feb 2026 | Dec 2025 | — | Feb 2026 | Bridgend | 7.2 |
| Pant y Wal (Extension)wind farm | wind farm | 5 | approved, not builtupdated Aug 2023 | Jan 2020 | granted Feb 2023 | Aug 2023 | Bridgend | 7.3 |
| National Road, Cilfynyddbattery storage | battery storage | 200 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | Rhondda Cynon Taf | 7.9 |
| Solar Array at Bryntail Roadsolar farm | solar farm | 39.9 | application submittedupdated Oct 2025 | May 2025 | — | Oct 2025 | Rhondda Cynon Taf | 8.0 |
| Whitehall Farm, Llanharry Roadsolar farm | solar farm | 1.3 | under constructionupdated Jul 2025 | Jul 2024 | granted Sep 2024 | Jul 2025 | Rhondda Cynon Taf | 8.3 |
| Agricultural Land at Trecastlesolar farm | solar farm | 4 | operationalupdated Jan 2016 | Mar 2015 | granted Oct 2015 | Jan 2016 | Rhondda Cynon Taf | 8.4 |
| Pen Rhiw Caradogsolar farm | solar farm | 4.7 | operationalupdated May 2017 | Sep 2013 | granted Jul 2016 | May 2017 | Rhondda Cynon Taf | 8.7 |
| Ty’n y Waun Solar Farm (Bridgend Energy Hub)solar farm | solar farm | 40 | approved, not builtupdated Dec 2024 | Jun 2023 | granted Oct 2024 | Dec 2024 | Bridgend | 9.0 |
| Pound Farm Lanebattery storage | battery storage | 200 | application submittedupdated Dec 2025 | Nov 2025 | — | Dec 2025 | Rhondda Cynon Taf | 9.0 |
| Upper Ogmore Wind Farmwind farm | wind farm | 25.2 | approved, not builtupdated Feb 2026 | Nov 2020 | granted Sep 2022 | Feb 2026 | Bridgend | 9.0 |
| Twyn Hywel Wind Farmwind farm | wind farm | 92.4 | approved, not builtupdated Feb 2026 | Jun 2023 | granted Nov 2024 | Feb 2026 | Caerphilly | 9.4 |
| Maes Mawr Solarsolar farm | solar farm | 30 | under constructionupdated Jul 2026 | Dec 2022 | granted Dec 2023 | Jul 2026 | Rhondda Cynon Taf | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Llanwonno Road, Ferndale Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Rhondda Cynon Taf | 4.7 |
| Rhiwfelin Fach Farm, Ynysmaerdysolar farm | solar farm | 0.5 | approved, not builtupdated Apr 2022 | Dec 2021 | granted Mar 2022 | Apr 2022 | Rhondda Cynon Taf | 5.3 |
| Coedcae Industrial Estate, Talbot Green - Micro Energy Storage Systemsbattery storage | battery storage | 0.2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 | Rhondda Cynon Taf | 7.5 |
| Upper Ogmore Wind Farmbattery storage | battery storage | — | approved, not builtupdated Oct 2022 | Nov 2020 | granted Sep 2022 | Oct 2022 | Bridgend | 9.0 |
| Midway Retail Parkrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | Rhondda Cynon Taf | 9.6 |
Distance from the average position of the CF39 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 4 | 6 | 3 | 0 | 170 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.9 |
| Wind farm | 18 | 2 | 4 | 8 | 0 | 190 |
| Wind turbine | 4 | 0 | 1 | 2 | 0 | 1.5 |
| Battery storage | 7 | 5 | 1 | 1 | 0 | 430 |
MW in pipeline: pending, approved and under-construction capacity.
How Rhondda Cynon Taf decides solar, wind and battery applications
| Applications | Rhondda Cynon Taf | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 5 (15%) | 19% |
| Solar refused | 0 of 13 | 12% |
| Onshore wind refused | 3 of 15 | 45% |
| Battery storage refused | 2 of 6 | 16% |
| Median time from submission to decision | 28.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 2 | — |
All projects in Rhondda Cynon Taf
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CF39, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.