Talbot Green, Llantrisant Solar Farm (9.9 MW)

Talbot Green, Llantrisant Solar Farm is a 9.9 MW solar farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 April 2024, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
5 December 2022Application submitted
25 April 2024Planning permission granted
25 April 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
9.9 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
Windel Energy
Planning authority
Rhondda Cynon Taf
Planning application reference
22/1413/10
Site area
19.1 ha
Address (REPD)
Talbot Green, Llantrisant
Council area (by location)
Rhondda Cynon Taf
Time to decision
72 weeks
Contracts for Difference
AR7a
Name in REPD
Talbot Green, Llantrisant - Solar Farm
REPD reference
9772

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Energy Centre Royal Mintbattery storage20operational0.2
Dyffryn Farm, Ynysmaerdysolar farm9.9application submitted0.8
Coed Ely Solar Farmsolar farm6under construction2.5
Mynydd Portref Wind Farm extensionwind farm12operational4.3
Mynydd Portrefwind farm9.4operational4.9
Berthlwyd Farmsolar farm5operational5.1
Taff Ely Wind Farmwind farm9operational5.5
Headwind Taff Ely Wind Farm (Repowering)wind farm17.5permission expired5.7
Pound Farm Lanebattery storage200application submitted6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5543, -3.3887).