Coed Ely Solar Farm (6 MW)

Coed Ely Solar Farm is a 6 MW solar farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 December 2024; the record was last updated on 1 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWsolar farm
under constructionstatus in REPD
1 April 2025record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
11 September 2023Application submitted
5 December 2023Planning permission granted
1 December 2024Construction started

Project details

Technology
solar farm
Capacity
6 MW
Status (REPD)
under construction
Record last updated
1 April 2025
Operator or applicant
Rhondda Cynon Taff County Borough Council
Planning authority
Rhondda Cynon Taf
Planning application reference
23/0994/08
Site area
16.9 ha
Address (REPD)
Former Coedely Colliery, Off A4119, Tonyrefail
Council area (by location)
Rhondda Cynon Taf
Time to decision
12 weeks
Name in REPD
Coed Ely - Solar Farm
REPD reference
13791

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dyffryn Farm, Ynysmaerdysolar farm9.9application submitted2.0
Mynydd Portref Wind Farm extensionwind farm12operational2.3
Energy Centre Royal Mintbattery storage20operational2.3
Talbot Green, Llantrisant Solar Farmsolar farm9.9approved, not built2.5
Mynydd Portrefwind farm9.4operational3.1
Taff Ely Wind Farmwind farm9operational3.2
Headwind Taff Ely Wind Farm (Repowering)wind farm17.5permission expired3.5
Trane Renewable Energy Parkwind farm11.9application withdrawn4.3
Mynydd Pen-y-Graig Wind Farmwind farm15application withdrawn5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5671, -3.4186).