Dyffryn Farm, Ynysmaerdy (9.9 MW solar farm)

Dyffryn Farm, Ynysmaerdy is a 9.9 MW solar farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 23 December 2025, no decision recorded; the record was last updated on 22 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.9 MWsolar farm
application submittedstatus in REPD
22 January 2026record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
23 December 2025Application submitted

Project details

Technology
solar farm
Capacity
9.9 MW
Status (REPD)
application submitted
Record last updated
22 January 2026
Operator or applicant
Windel Solar 8 Limited
Planning authority
Rhondda Cynon Taf
Planning application reference
25/1280/FUL
Site area
20.9 ha
Address (REPD)
Dyffryn Farm, Ynysmaerdy, Pontyclun
Council area (by location)
Rhondda Cynon Taf
Name in REPD
Dyffryn Farm, Ynysmaerdy - Solar Panels
REPD reference
18881

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Energy Centre Royal Mintbattery storage20operational0.7
Talbot Green, Llantrisant Solar Farmsolar farm9.9approved, not built0.8
Coed Ely Solar Farmsolar farm6under construction2.0
Mynydd Portref Wind Farm extensionwind farm12operational3.5
Mynydd Portrefwind farm9.4operational4.1
Taff Ely Wind Farmwind farm9operational4.8
Headwind Taff Ely Wind Farm (Repowering)wind farm17.5permission expired5.0
Berthlwyd Farmsolar farm5operational5.8
Trane Renewable Energy Parkwind farm11.9application withdrawn6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5533, -3.4004).