Energy Projects Near You

Energy Centre Royal Mint (20 MW battery storage)

Energy Centre Royal Mint is a 20 MW battery storage project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2023; the record was last updated on 1 August 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
operationalstatus in REPD
1 August 2023record last updated
Rhondda Cynon Tafcouncil area

Planning timeline

DateStage
23 September 2019Application submitted
22 January 2020Planning permission granted
1 May 2022Construction started
1 August 2023Operational

Project details

Technology
battery storage (co-located with fossil fuel plant)
Capacity
20 MW
Status (REPD)
operational
Record last updated
1 August 2023
Operator or applicant
Infinite Energy Renewables
Planning authority
Rhondda Cynon Taf
Planning application reference
19/1007/10
Address (REPD)
Royal Mint, Llantrisant, Pontyclun, Mid Glamorgan
Council area (by location)
Rhondda Cynon Taf
Time to decision
17 weeks
REPD reference
7684

Who decides

ApplicationsRhondda Cynon TafUK
Decided applications (solar, wind, battery)3410,236
Refused5 (15%)19%
Solar refused0 of 1312%
Onshore wind refused3 of 1545%
Battery storage refused2 of 616%
Median time from submission to decision28.9 weeks17.0 weeks
Appeals lodged / allowed0 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Talbot Green, Llantrisant Solar Farmsolar farm9.9approved, not built0.2
Dyffryn Farm, Ynysmaerdysolar farm9.9application submitted0.7
Coed Ely Solar Farmsolar farm6under construction2.3
Mynydd Portref Wind Farm extensionwind farm12operational4.1
Mynydd Portrefwind farm9.4operational4.8
Berthlwyd Farmsolar farm5operational5.1
Taff Ely Wind Farmwind farm9operational5.4
Headwind Taff Ely Wind Farm (Repowering)wind farm17.5permission expired5.6
Llanwonno Wind Farmsolar farm30.7application submitted6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.555, -3.3908).