Blaencorrwg Wind Farm (19.3 MW)
Blaencorrwg Wind Farm is a 19.3 MW wind farm project in Rhondda Cynon Taf, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 3 November 1994; the record was last updated on 29 September 2003.
19.3 MWwind farm
refusedstatus in REPD
29 September 2003record last updated
Rhondda Cynon Tafcouncil area
Planning timeline
| Date | Stage |
|---|---|
| 25 July 1994 | Application submitted |
| 3 November 1994 | Refused by the planning authority |
Project details
- Technology
- wind farm
- Capacity
- 19.3 MW
- Status (REPD)
- refused
- Record last updated
- 29 September 2003
- Operator or applicant
- Ecogen
- Planning authority
- Neath Port Talbot
- Planning application reference
- 93/9291
- Address (REPD)
- Gwaun Blaencorrwg Nr Glyncorrwg Port Talbot West Glamorgan
- Council area (by location)
- Rhondda Cynon Taf
- Time to decision
- 14 weeks
- REPD reference
- 3509
Who decides
| Applications | Neath Port Talbot | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 10 (26%) | 19% |
| Solar refused | 0 of 12 | 12% |
| Onshore wind refused | 10 of 23 | 45% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 57.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Ffynnon Oer Wind Farm | wind farm | 32 | operational | 3.2 |
| Hendre Fawr Farm | solar farm | 11.6 | operational | 4.4 |
| Melin Court | wind farm | 18 | approved, not built | 5.2 |
| Maerdy | wind farm | 24 | operational | 5.2 |
| Rhigos Road Solar Farm | solar farm | 9.9 | under construction | 5.4 |
| Bryngolwg Farm, Hirwaun Solar farm | solar farm | 8.9 | operational | 5.5 |
| Maesgwyn Wind Farm - extension (Phase 2) | wind farm | 7 | permission expired | 5.6 |
| Cefn Farm, Mount Road | battery storage | 200 | application submitted | 5.7 |
| Hirwaun Stor Generation | battery storage | 21.8 | operational | 5.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7014, -3.5932).