Maesgwyn Wind Farm - extension (Phase 2) (7 MW)

Maesgwyn Wind Farm - extension (Phase 2) is a 7 MW wind farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 17 December 2020; the record was last updated on 27 January 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWwind farm
permission expiredstatus in REPD
27 January 2020record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
15 August 2014Application submitted
17 December 2015Planning permission granted
17 December 2020Permission expired

Project details

Technology
wind farm
Capacity
7 MW
Status (REPD)
permission expired
Record last updated
27 January 2020
Operator or applicant
Pennant Walters (MAESX)
Planning authority
Neath Port Talbot
Planning application reference
P2014/0733
Turbines
3
Address (REPD)
Maesgwyn Wind Farm Between Onllwyn & Glynneath
Council area (by location)
Neath Port Talbot
Time to decision
70 weeks
REPD reference
6335

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Maesgwynwind farm26operational1.1
Maesgwyn solar farmsolar farm7.5operational3.2
Hendre Fawr Farmsolar farm11.6operational3.6
Dulais Valleywind farm13.5refused4.3
Hirfynyddwind farm18refused on appeal5.2
Melin Courtwind farm18approved, not built5.6
Blaencorrwg Wind Farmwind farm19.3refused5.6
Bryngolwg Farm, Hirwaun Solar farmsolar farm8.9operational6.3
Ffynnon Oer Wind Farmwind farm32operational6.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7406, -3.6442).