Hirfynydd (18 MW wind farm)

Hirfynydd is an 18 MW wind farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 4 September 2015; the record was last updated on 5 October 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
refused on appealstatus in REPD
5 October 2015record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
17 January 2008Application submitted
12 November 2013Refused by the planning authority
20 January 2014Appeal lodged
4 September 2015Appeal refused

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
refused on appeal
Record last updated
5 October 2015
Operator or applicant
Wind Ventures (Acciona Energy)
Planning authority
Neath Port Talbot
Planning application reference
P2008/0024
Appeal reference
APP/Y6930/A/13/2209942
Turbines
9
Address (REPD)
Farmland to the East of Crynant and Seven Sisters adjoining forestry at Hirfynydd
Council area (by location)
Neath Port Talbot
Time to decision
304 weeks
REPD reference
4539

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dulais Valleywind farm13.5refused0.9
Pencaerlan Solar Farmsolar farm25application submitted3.0
Maesgwynwind farm26operational4.1
Land South of Ystalyferawind farm12refused4.3
Varteg Hillwind farm12refused4.3
Mynydd Marchywel Wind Farmwind farm10refused on appeal5.0
Maesgwyn Wind Farm - extension (Phase 2)wind farm7permission expired5.2
Melin Courtwind farm18approved, not built6.4
Maesgwyn solar farmsolar farm7.5operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7396, -3.7194).