Energy Projects Near You

Foel Trawsnant (35 MW wind farm)

Foel Trawsnant is a 35 MW wind farm project in Bridgend, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 November 2021, not yet built; the record was last updated on 31 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWwind farm
approved, not builtstatus in REPD
31 October 2023record last updated
Bridgendcouncil area

Planning timeline

DateStage
20 October 2014Application submitted
25 November 2021Planning permission granted
15 June 2027Permission due to expire (unless work starts)

Project details

Technology
wind farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
31 October 2023
Operator or applicant
Pennant Walters Ltd
Planning authority
Neath Port Talbot
Planning application reference
P2014/0825
Turbines
8
Turbine height
145 m
Address (REPD)
Foel Trawsnant, Bryn, Port Talbot
Council area (by location)
Bridgend
Time to decision
370 weeks
Contracts for Difference
AR5
REPD reference
4764

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Foel Fawrsolar farm5.1permission expired3.0
Pen Y Cymoeddwind farm228operational3.5
Pen y Cymoedd Energy Storagebattery storage22operational3.5
Y Bryn Wind Farmwind farm130refused4.0
Tonmawr - Mynydd Fforch Dwm Wind Farmwind farm35approved, not built4.3
Llynfi Renewable Energy Park, Land at Mynydd Caerauwind farm24operational5.0
Llynfi Afan Renewable Energy Parkwind farm6operational5.3
Pant-Y-Moch Farmsolar farm5operational6.1
Mynydd Brombil Wind Farmwind farm8operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6244, -3.6851).