Mynydd Brombil Wind Farm (8 MW)

Mynydd Brombil Wind Farm is an 8 MW wind farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 January 2017; the record was last updated on 18 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWwind farm
operationalstatus in REPD
18 April 2017record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
29 August 2012Application submitted
7 January 2015Appeal lodged
8 July 2015Planning permission granted
8 July 2015Appeal allowed
1 February 2016Construction started
15 January 2017Operational

Project details

Technology
wind farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
18 April 2017
Operator or applicant
REG Windpower
Planning authority
Neath Port Talbot
Planning application reference
P2012/0638
Appeal reference
APP/Y6930/A/14/2226525
Turbines
4
Address (REPD)
Brombil, Port Talbot
Council area (by location)
Neath Port Talbot
Time to decision
149 weeks
REPD reference
4193

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Rhydypandy Road, Morristonbattery storage100approved, not built0.3
Pant-Y-Moch Farmsolar farm5operational2.3
Y Bryn Wind Farmwind farm130refused2.7
Tylerfedwen Farm Solar Parksolar farm13.3permission expired5.6
Ton Marw Farmwind farm7.3refused5.7
Foel Trawsnantwind farm35approved, not built6.2
Baglan Bay Solar Farm - Phase 1solar farm5operational6.5
Baglan Bay Solar Farm - Phase 2solar farm10application withdrawn6.7
Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage Systembattery storage30approved, not built7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.583, -3.7457).