Energy Projects Near You

Baglan Bay Solar Farm - Phase 2 (10 MW)

Baglan Bay Solar Farm - Phase 2 is a 10 MW solar farm project in Neath Port Talbot, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 11 March 2020; the record was last updated on 31 March 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
application withdrawnstatus in REPD
31 March 2020record last updated
Neath Port Talbotcouncil area

Planning timeline

DateStage
6 May 2015Application submitted
11 March 2020Application withdrawn

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
application withdrawn
Record last updated
31 March 2020
Operator or applicant
St. Modwen Developments
Planning authority
Neath Port Talbot
Planning application reference
P2015/0304
Site area
20.6 ha
Address (REPD)
Land adjacent to, Central Aven, Baglan Energy Park, Baglan, Phase 1, Port Talbot, West Glamorgan
Council area (by location)
Neath Port Talbot
REPD reference
5223

Who decides

ApplicationsNeath Port TalbotUK
Decided applications (solar, wind, battery)3810,236
Refused10 (26%)19%
Solar refused0 of 1212%
Onshore wind refused10 of 2345%
Battery storage refused0 of 316%
Median time from submission to decision57.9 weeks17.0 weeks
Appeals lodged / allowed4 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: Neath Port Talbort, Neath Port Talbot.

Other large projects within 10 km

ProjectTypeMWStatuskm
Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage Systembattery storage30approved, not built0.9
Baglan Bay Solar Farm - Phase 1solar farm5operational1.2
Ton Marw Farmwind farm7.3refused2.4
Tylerfedwen Farm Solar Parksolar farm13.3permission expired2.8
Pant-Y-Moch Farmsolar farm5operational4.6
John Green Frog Power Compound, John North Road Battery Systembattery storage20approved, not built5.3
Carn Nicholas Farmsolar farm5application withdrawn6.2
Carn Nicholas Farmsolar farm5under construction6.2
Carn Nicholas Farm (Extension)solar farm10operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.619, -3.823).