John Green Frog Power Compound, John North Road Battery System (20 MW)

John Green Frog Power Compound, John North Road Battery System is a 20 MW battery storage project in Swansea, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 20 January 2023, not yet built; the record was last updated on 24 January 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
approved, not builtstatus in REPD
24 January 2023record last updated
Swanseacouncil area

Planning timeline

DateStage
17 October 2022Application submitted
20 January 2023Planning permission granted
20 January 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
24 January 2023
Operator or applicant
Green Frog Power Limited
Planning authority
Swansea
Planning application reference
2022/2356/FUL
Address (REPD)
Tir John Green Frog Power Compound Tir, John North Road, Port Tennant
Council area (by location)
Swansea
Time to decision
14 weeks
Name in REPD
John Green Frog Power Compound, John North Road - Battery System
REPD reference
12455

Who decides

ApplicationsSwanseaUK
Decided applications (solar, wind, battery)3510,236
Refused9 (26%)19%
Solar refused5 of 2012%
Onshore wind refused2 of 345%
Battery storage refused2 of 1216%
Median time from submission to decision18.1 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Carn Nicholas Farm (Extension)solar farm10operational1.1
Carn Nicholas Farmsolar farm5under construction1.1
Carn Nicholas Farmsolar farm5application withdrawn1.1
Baglan Bay Solar Farm - Phase 1solar farm5operational5.1
Chosen Park, Baglan Energy Park - Unit 3 - Battery Storage Systembattery storage30approved, not built5.1
Baglan Bay Solar Farm - Phase 2solar farm10application withdrawn5.3
Ton Marw Farmwind farm7.3refused5.9
Bryntywod, Llangyfelachbattery storage200approved, not built7.1
Craig Y Perchych, Glais Solar farmsolar farm20approved, not built7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6252, -3.8985).