Saron Road solar park (6.7 MW)
Saron Road solar park is a 6.7 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 February 2015; the record was last updated on 11 August 2015.
6.7 MWsolar farm
operationalstatus in REPD
11 August 2015record last updated
Carmarthenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 12 April 2013 | Application submitted |
| 19 September 2013 | Planning permission granted |
| 24 November 2014 | Construction started |
| 15 February 2015 | Operational |
Project details
- Technology
- solar farm
- Capacity
- 6.7 MW
- Status (REPD)
- operational
- Record last updated
- 11 August 2015
- Operator or applicant
- Anesco
- Planning authority
- Carmarthenshire
- Planning application reference
- E/28054
- Site area
- 16.4 ha
- Address (REPD)
- E/O Saron Road, N/O Dyffryn Road, Saron, Ammanford, Dyfed
- Council area (by location)
- Carmarthenshire
- Time to decision
- 23 weeks
- REPD reference
- 2355
Who decides
| Applications | Carmarthenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 10 (16%) | 19% |
| Solar refused | 5 of 34 | 12% |
| Onshore wind refused | 5 of 14 | 45% |
| Battery storage refused | 0 of 13 | 16% |
| Median time from submission to decision | 21.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Pen Y Cae solar farm | solar farm | 6.9 | operational | 1.1 |
| Clawdd Ddu PV | solar farm | 13.5 | operational | 3.0 |
| Tycroes Solar Farm | solar farm | 40 | approved, not built | 3.2 |
| Brynrhyd Solar Farm | solar farm | 36 | approved, not built | 4.9 |
| Cefn Betingau Farm | solar farm | 9 | operational | 5.1 |
| Mynydd y Betws | wind farm | 34.5 | operational | 6.6 |
| Mynydd Y Gwair Wind Farm | wind farm | 32.8 | operational | 7.5 |
| Pentre farm | solar farm | 5.5 | operational | 8.2 |
| Coed Bach Park, Gwynfryn Road | rooftop solar | 15 | application submitted | 9.5 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7953, -4.0184).