Parc Solar Caenewydd (42 MW)

Parc Solar Caenewydd is a 42 MW solar farm project in Swansea, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 May 2026; the record was last updated on 17 June 2026. It is decided by the Welsh Government as a development of national significance.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWsolar farm
under constructionstatus in REPD
17 June 2026record last updated
Swanseacouncil area

Planning timeline

DateStage
12 June 2024Application submitted
2 December 2024Planning permission granted
1 May 2026Construction started

Project details

Technology
solar farm
Capacity
42 MW
Status (REPD)
under construction
Record last updated
17 June 2026
Operator or applicant
Infinis Solar Developments
Planning authority
Welsh Government (NSIP)
Planning application reference
CAS-01900-V0J7C7
Site area
83.2 ha
Address (REPD)
Parc Solar Caenewydd Swansea Road Gorseinon Swansea
Council area (by location)
Swansea
Time to decision
25 weeks
Contracts for Difference
AR7a
REPD reference
11302

The scheme also includes 46 MW of battery storage, recorded separately in REPD (under construction).

Who decides

It is decided by the Welsh Government as a development of national significance. Welsh Government (NSIP) refused 22% of 55 decided solar, wind and battery applications in REPD (median 67 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Bryntywod, Llangyfelachbattery storage200approved, not built4.0
Gwenlais Solar Farmsolar farm16.3approved, not built4.2
Castell Ddu Solar Farmsolar farm5permission expired4.6
Solar Farm at The E/O Pontlliwsolar farm40application submitted5.2
Gelliwern Isaf Farmsolar farm6operational5.2
Lletty Scilp Farm, Swansea Northbattery storage400approved, not built5.6
Land at Lltty Morphil Farmsolar farm5abandoned5.6
Abergelli Farm, Felindrebattery storage250application submitted6.2
Coed Bach Park, Gwynfryn Roadrooftop solar15application submitted6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6546, -4.0118).