Energy Projects Near You

Land South Of Bryn Cyrnau Isaf (5.9 MW solar farm)

Land South Of Bryn Cyrnau Isaf is a 5.9 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 1 February 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.9 MWsolar farm
operationalstatus in REPD
1 February 2018record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
9 March 2015Application submitted
9 June 2015Planning permission granted
31 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
5.9 MW
Status (REPD)
operational
Record last updated
1 February 2018
Operator or applicant
Green Switch Solutions - Liquidated
Planning authority
Carmarthenshire
Planning application reference
W/31690
Site area
13.8 ha
Address (REPD)
Land South Of, Bryn Cyrnau Isaf, Cwmffrwd, Carmarthen
Council area (by location)
Carmarthenshire
Time to decision
13 weeks
REPD reference
5271

Earlier applications for this site

ApplicationMWSubmittedOutcome
Bryn Cyrnau Isaf W/30204623 May 2014refused 19 December 2014

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bryncoch Solar Farmsolar farm19abandoned8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8338, -4.2807).