Energy Projects Near You

Solar, wind and battery projects near Carmarthen (SA32)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA32 (Carmarthenshire): 1 approved but not yet running, 2 operational. The largest live scheme is Nantycaws Waste Management Facility, Llanddarog Solar Farm (2 MW solar farm, approved on 17 December 2024, not yet built), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
1approved, not running
2operational

Projects within 10 km of SA32

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Nantycaws Waste Management Facility, Llanddarog Solar Farmsolar farmsolar farm2approved, not builtupdated Jan 2025Sep 2024granted Dec 2024Jan 2025Carmarthenshire6.5
Brechfa Forest Westwind farmwind farm57.4operationalupdated Sep 2018Nov 2011granted Mar 2013Sep 2018Carmarthenshire8.7
Pistyllgwyn Farmsolar farmsolar farm1.5permission expiredupdated Aug 2019Aug 2015granted Dec 2015Aug 2019Carmarthenshire9.6
Land South Of Bryn Cyrnau Isafsolar farmsolar farm5.9operationalupdated Feb 2018Mar 2015granted Jun 2015Feb 2018Carmarthenshire9.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Towy Retail Park, Old Llangunnor Roadrooftop solarrooftop solar—refusedupdated Jul 2026Apr 2026refused Jun 2026Jul 2026Carmarthenshire9.9

Distance from the average position of the SA32 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm301102
Rooftop solar100010
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Carmarthenshire decides solar, wind and battery applications

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Carmarthenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.