Energy Projects Near You

Solar, wind and battery projects near Pencader (SA39)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA39 (Carmarthenshire): 1 is waiting for a planning decision, 1 operational. The largest live scheme is Tymaen Farm, Rhos (4.9 MW solar farm, application submitted on 2 April 2026, no decision recorded), 7.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
1awaiting a decision
0approved, not running
1operational

Projects within 10 km of SA39

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Blaengwenwind farmwind farm23operationalupdated Apr 2010Jul 2006granted Mar 2007Apr 2010Carmarthenshire4.6
Bryn Llywelynwind farmwind farm48.3refused on appealupdated May 2016Dec 2010refused Dec 2012May 2016Carmarthenshire5.9
Tymaen Farm, Rhossolar farmsolar farm4.9application submittedupdated May 2026Apr 2026—May 2026Carmarthenshire7.1

Distance from the average position of the SA39 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110004.9
Wind farm200110

MW in pipeline: pending, approved and under-construction capacity.

How Carmarthenshire decides solar, wind and battery applications

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Carmarthenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.