Energy Projects Near You

Solar, wind and battery projects near Lampeter (SA48)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA48 (Ceredigion): 1 approved but not yet running, 1 operational. The largest live scheme is Cambrian Cross Country, Trefilan (0.5 MW wind turbine, approved on 21 August 2025, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
1approved, not running
1operational

Projects within 10 km of SA48

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Nanthenfoel Farmssolar farmsolar farm5operationalupdated Mar 2017Jul 2015granted Nov 2015Mar 2017Ceredigion1.6
Maesygarnsolar farmsolar farm10abandonedupdated Nov 2018Aug 2015granted Aug 2016Nov 2018Ceredigion8.0
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cambrian Cross Country, Trefilanwind turbinewind turbine0.5approved, not builtupdated Nov 2025Nov 2024granted Aug 2025Nov 2025Ceredigion7.6

Distance from the average position of the SA48 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200100
Wind turbine101000.5

MW in pipeline: pending, approved and under-construction capacity.

How Ceredigion decides solar, wind and battery applications

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Ceredigion

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.