Energy Projects Near You

Solar, wind and battery projects near Tregaron (SY25)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of SY25 (Ceredigion): 1 operational. The largest scheme is Llangwyryfon (9.4 MW wind farm, operational since 1 February 2004), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
0approved, not running
1operational

Projects within 10 km of SY25

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Llangwyryfonwind farmwind farm9.4operationalupdated Mar 2010Dec 2001granted Mar 2003Mar 2010Ceredigion9.9

Distance from the average position of the SY25 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Ceredigion decides solar, wind and battery applications

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Ceredigion

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.