Energy Projects Near You

Solar, wind and battery projects near Aberystwyth (SY23)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY23 (Ceredigion): 3 approved but not yet running, 2 operational. The largest live scheme is National Library Of Wales, Penglais (0.4 MW solar farm, approved on 31 January 2024, not yet built), 4.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
3approved, not running
2operational

Projects within 10 km of SY23

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fferm Penglais Solar Farmsolar farmsolar farm2.5operationalupdated Oct 2022May 2021granted Oct 2021Oct 2022Ceredigion5.2
Llangwyryfonwind farmwind farm9.4operationalupdated Mar 2010Dec 2001granted Mar 2003Mar 2010Ceredigion8.2
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rhodfa Padarn, Llanbadarn Fawrrooftop solarrooftop solar0.2approved, not builtupdated May 2022Mar 2022granted Sep 2022May 2022Ceredigion3.4
National Library Of Wales, Penglaissolar farmsolar farm0.4approved, not builtupdated Feb 2024Feb 2023granted Jan 2024Feb 2024Ceredigion4.1
National Library Of Wales, Penglais Solar Arraysrooftop solarrooftop solar0.3approved, not builtupdated Mar 2024Feb 2023granted Feb 2024Mar 2024Ceredigion4.1

Distance from the average position of the SY23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201100.4
Rooftop solar202000.5
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Ceredigion decides solar, wind and battery applications

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Ceredigion

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.