Energy Projects Near You

Llangwyryfon (9.4 MW wind farm)

Llangwyryfon is a 9.4 MW wind farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 February 2004; the record was last updated on 3 March 2010.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.4 MWwind farm
operationalstatus in REPD
3 March 2010record last updated
Ceredigioncouncil area

Planning timeline

DateStage
1 December 2001Application submitted
1 March 2003Planning permission granted
1 February 2004Operational

Project details

Technology
wind farm
Capacity
9.4 MW
Status (REPD)
operational
Record last updated
3 March 2010
Operator or applicant
Westbury Windfarms
Planning authority
Ceredigion
Planning application reference
A01/1330
Turbines
11
Address (REPD)
Llangwyryfon, Southeast Aberystwyth Ceredigion
Council area (by location)
Ceredigion
Time to decision
65 weeks
REPD reference
3229

Who decides

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3069, -4.0292).