Energy Projects Near You

Solar, wind and battery projects near Aberaeron (SA46)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA46 (Ceredigion): 2 approved but not yet running. The largest live scheme is Cambrian Cross Country, Trefilan (0.5 MW wind turbine, approved on 21 August 2025, not yet built), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
2approved, not running
0operational

Projects within 10 km of SA46

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pant Cefn Farmsolar farmsolar farm2.9permission expiredupdated Nov 2018Oct 2015granted Jul 2016Nov 2018Ceredigion5.2
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Monachty Bach, Pennantrooftop solarrooftop solar0.4approved, not builtupdated Nov 2025Jun 2025granted Aug 2025Nov 2025Ceredigion4.7
Cambrian Cross Country, Trefilanwind turbinewind turbine0.5approved, not builtupdated Nov 2025Nov 2024granted Aug 2025Nov 2025Ceredigion9.5

Distance from the average position of the SA46 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100000
Rooftop solar101000.4
Wind turbine101000.5

MW in pipeline: pending, approved and under-construction capacity.

How Ceredigion decides solar, wind and battery applications

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Ceredigion

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.