Energy Projects Near You

Solar, wind and battery projects near New Quay (SA45)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA45 (Ceredigion): none of them is pending, approved or operational. The largest scheme is Rhos Garn Whirlgarn (6 MW wind farm, refused on appeal on 6 July 2016), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of SA45

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Pant Cefn Farmsolar farmsolar farm2.9permission expiredupdated Nov 2018Oct 2015granted Jul 2016Nov 2018Ceredigion4.6
Rhos Garn Whirlgarnwind farmwind farm6refused on appealupdated Aug 2016Feb 2015refused May 2015Aug 2016Ceredigion9.4

Distance from the average position of the SA45 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100000
Wind farm100010

MW in pipeline: pending, approved and under-construction capacity.

How Ceredigion decides solar, wind and battery applications

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Ceredigion

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.