Solar, wind and battery projects near Llandysul (SA44)
2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA44 (Ceredigion): none of them is pending, approved or operational. The largest scheme is Rhos Garn Whirlgarn (6 MW wind farm, refused on appeal on 6 July 2016), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SA44
Projects of 1 MW and more (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Rhos Garn Whirlgarnwind farm | wind farm | 6 | refused on appealupdated Aug 2016 | Feb 2015 | refused May 2015 | Aug 2016 | Ceredigion | 9.7 |
| Blaenffos Wind Turbineswind farm | wind farm | 1 | refused on appealupdated Aug 2018 | Jul 2014 | refused Jun 2015 | Aug 2018 | Carmarthenshire | 9.7 |
Distance from the average position of the SA44 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Wind farm | 2 | 0 | 0 | 0 | 2 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Ceredigion decides solar, wind and battery applications
| Applications | Ceredigion | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 2 (11%) | 19% |
| Solar refused | 0 of 12 | 12% |
| Onshore wind refused | 2 of 7 | 45% |
| Median time from submission to decision | 35.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.