Energy Projects Near You

Solar, wind and battery projects near Llandysul (SA44)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA44 (Ceredigion): none of them is pending, approved or operational. The largest scheme is Rhos Garn Whirlgarn (6 MW wind farm, refused on appeal on 6 July 2016), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
0awaiting a decision
0approved, not running
0operational

Projects within 10 km of SA44

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rhos Garn Whirlgarnwind farmwind farm6refused on appealupdated Aug 2016Feb 2015refused May 2015Aug 2016Ceredigion9.7
Blaenffos Wind Turbineswind farmwind farm1refused on appealupdated Aug 2018Jul 2014refused Jun 2015Aug 2018Carmarthenshire9.7

Distance from the average position of the SA44 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Wind farm200020

MW in pipeline: pending, approved and under-construction capacity.

How Ceredigion decides solar, wind and battery applications

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Ceredigion

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.