Energy Projects Near You

Solar, wind and battery projects near Llanybydder (SA40)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SA40 (Carmarthenshire): 1 approved but not yet running, 1 operational. The largest live scheme is Mynydd Pencarreg (4.6 MW wind farm, approved on 8 March 2016, not yet built), 7.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
0awaiting a decision
1approved, not running
1operational

Projects within 10 km of SA40

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Maesygarnsolar farmsolar farm10abandonedupdated Nov 2018Aug 2015granted Aug 2016Nov 2018Ceredigion5.3
Mynydd Pencarregwind farmwind farm4.6approved, not builtupdated Feb 2026Mar 2015granted Mar 2016Feb 2026Carmarthenshire7.2
Nanthenfoel Farmssolar farmsolar farm5operationalupdated Mar 2017Jul 2015granted Nov 2015Mar 2017Ceredigion7.9
Bryn Llywelynwind farmwind farm48.3refused on appealupdated May 2016Dec 2010refused Dec 2012May 2016Carmarthenshire8.4
Rhos Garn Whirlgarnwind farmwind farm6refused on appealupdated Aug 2016Feb 2015refused May 2015Aug 2016Ceredigion9.1

Distance from the average position of the SA40 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200100
Wind farm301024.6

MW in pipeline: pending, approved and under-construction capacity.

How Carmarthenshire decides solar, wind and battery applications

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Carmarthenshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.