Energy Projects Near You

Nanthenfoel Farms (5 MW solar farm)

Nanthenfoel Farms is a 5 MW solar farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 21 March 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
21 March 2017record last updated
Ceredigioncouncil area

Planning timeline

DateStage
27 July 2015Application submitted
18 November 2015Planning permission granted
30 November 2016Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
21 March 2017
Operator or applicant
Anesco
Planning authority
Ceredigion
Planning application reference
A150516
Site area
15.8 ha
Address (REPD)
Land At Nanthenfoel Farm, Creuddyn Bridge, Lampeter
Council area (by location)
Ceredigion
Time to decision
16 weeks
REPD reference
5540

Who decides

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Maesygarnsolar farm10abandoned6.9
Rhos Garn Whirlgarnwind farm6refused on appeal9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1511, -4.1352).