Bryn Llywelyn (48.3 MW wind farm)

Bryn Llywelyn is a 48.3 MW wind farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 18 December 2012; the record was last updated on 31 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

48.3 MWwind farm
refused on appealstatus in REPD
31 May 2016record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
14 December 2010Application submitted
18 December 2012Refused by the planning authority
18 December 2012Appeal refused
29 April 2016Appeal lodged

Project details

Technology
wind farm
Capacity
48.3 MW
Status (REPD)
refused on appeal
Record last updated
31 May 2016
Operator or applicant
Renewable Energy Systems (RES)
Planning authority
Carmarthenshire
Planning application reference
E/23947
Appeal reference
APP/M6825/A/16/3149642
Turbines
21
Address (REPD)
Llanllwni,
Council area (by location)
Carmarthenshire
Time to decision
105 weeks
REPD reference
3790

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brechfa Forest East Wind Farmwind farm36abandoned5.4
Brechfa Forest Westwind farm57.4operational5.9
Blaengwenwind farm23operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0089, -4.1592).