Solar, wind and battery projects near Llandeilo (SA19)
1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of SA19 (Carmarthenshire): 1 approved but not yet running. The largest live scheme is Beechwood Industrial Estate - Micro Energy Storage (0.2 MW battery storage, approved on 9 October 2025, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SA19
Smaller schemes under 1 MW, mostly rooftop solar (1)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Beechwood Industrial Estate - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | Jun 2025 | granted Oct 2025 | Nov 2025 | Carmarthenshire | 7.6 |
Distance from the average position of the SA19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Battery storage | 1 | 0 | 1 | 0 | 0 | 0.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Carmarthenshire decides solar, wind and battery applications
| Applications | Carmarthenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 10 (16%) | 19% |
| Solar refused | 5 of 34 | 12% |
| Onshore wind refused | 5 of 14 | 45% |
| Battery storage refused | 0 of 13 | 16% |
| Median time from submission to decision | 21.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
All projects in Carmarthenshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.