Energy Projects Near You

Bryncoch Solar Farm (19 MW)

Bryncoch Solar Farm is a 19 MW solar farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 21 October 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
abandonedstatus in REPD
21 October 2019record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
15 June 2015Application submitted
11 September 2015Planning permission granted
11 September 2020Permission expired

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
abandoned
Record last updated
21 October 2019
Operator or applicant
Green Energy UK Direct
Planning authority
Carmarthenshire
Planning application reference
W/32171
Site area
41.6 ha
Address (REPD)
Bryncoch, Ferryside, Dyfed
Council area (by location)
Carmarthenshire
Time to decision
13 weeks
REPD reference
5462

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land South Of Bryn Cyrnau Isafsolar farm5.9operational8.1
Ffos Las Racecoursesolar farm5.5operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7725, -4.3454).