Blaen Bowi Wind Farm (Extension) (9.1 MW)

Blaen Bowi Wind Farm (Extension) is a 9.1 MW wind farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 June 2009; the record was last updated on 12 September 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.1 MWwind farm
refused on appealstatus in REPD
12 September 2011record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
26 April 2005Application submitted
28 September 2007Refused by the planning authority
10 June 2009Appeal refused

Project details

Technology
wind farm
Capacity
9.1 MW
Status (REPD)
refused on appeal
Record last updated
12 September 2011
Operator or applicant
Windjen Power Ltd / Dulas Ltd
Planning authority
Carmarthenshire
Planning application reference
W/09828
Turbines
3
Address (REPD)
BLAEN BOWI WIND FARM LAN FARM CAPEL IWAN NEWCASTLE EMLYN
Council area (by location)
Carmarthenshire
Time to decision
126 weeks
REPD reference
3240

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blaen Bowi Solar parksolar farm8abandoned0.8
Blaen Bowisolar5.7permission expired0.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9971, -4.4413).