Blaen Bowi Wind Farm (Extension) (9.1 MW)
Blaen Bowi Wind Farm (Extension) is a 9.1 MW wind farm project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 June 2009; the record was last updated on 12 September 2011.
9.1 MWwind farm
refused on appealstatus in REPD
12 September 2011record last updated
Carmarthenshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 26 April 2005 | Application submitted |
| 28 September 2007 | Refused by the planning authority |
| 10 June 2009 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 9.1 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 12 September 2011
- Operator or applicant
- Windjen Power Ltd / Dulas Ltd
- Planning authority
- Carmarthenshire
- Planning application reference
- W/09828
- Turbines
- 3
- Address (REPD)
- BLAEN BOWI WIND FARM LAN FARM CAPEL IWAN NEWCASTLE EMLYN
- Council area (by location)
- Carmarthenshire
- Time to decision
- 126 weeks
- REPD reference
- 3240
Who decides
| Applications | Carmarthenshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 61 | 10,236 |
| Refused | 10 (16%) | 19% |
| Solar refused | 5 of 34 | 12% |
| Onshore wind refused | 5 of 14 | 45% |
| Battery storage refused | 0 of 13 | 16% |
| Median time from submission to decision | 21.8 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Blaen Bowi Solar park | solar farm | 8 | abandoned | 0.8 |
| Blaen Bowi | solar | 5.7 | permission expired | 0.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9971, -4.4413).