Energy Projects Near You

Blaen Bowi (5.7 MW solar)

Blaen Bowi is a 5.7 MW solar project in Carmarthenshire, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 24 February 2017; the record was last updated on 18 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.7 MWsolar
permission expiredstatus in REPD
18 July 2018record last updated
Carmarthenshirecouncil area

Planning timeline

DateStage
18 January 2012Application submitted
24 February 2012Planning permission granted
24 February 2017Permission expired

Project details

Technology
solar
Capacity
5.7 MW
Status (REPD)
permission expired
Record last updated
18 July 2018
Operator or applicant
Novus Solar Developments
Planning authority
Carmarthenshire
Planning application reference
W/26003
Address (REPD)
Capel Iwan, Newcastle, Emlyn, Carmarthenshire
Council area (by location)
Carmarthenshire
Time to decision
5 weeks
REPD reference
1941

Who decides

ApplicationsCarmarthenshireUK
Decided applications (solar, wind, battery)6110,236
Refused10 (16%)19%
Solar refused5 of 3412%
Onshore wind refused5 of 1445%
Battery storage refused0 of 1316%
Median time from submission to decision21.8 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blaen Bowi Solar parksolar farm8abandoned<0.1
Blaen Bowi Wind Farm (Extension)wind farm9.1refused on appeal0.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9899, -4.4445).