Energy Projects Near You

Blaenporth Solar Farm (7 MW)

Blaenporth Solar Farm is a 7 MW solar farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 3 September 2017; the record was last updated on 26 November 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
permission expiredstatus in REPD
26 November 2019record last updated
Ceredigioncouncil area

Planning timeline

DateStage
22 May 2014Application submitted
3 September 2014Planning permission granted
3 September 2017Permission expired

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
permission expired
Record last updated
26 November 2019
Operator or applicant
Juwi Renewable Energies
Planning authority
Ceredigion
Planning application reference
A140370
Address (REPD)
Blaenporth, Cardigan
Council area (by location)
Ceredigion
Time to decision
15 weeks
REPD reference
1327

Who decides

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Llwyn Du Solar Farmsolar farm8operational0.9
Crugmore Farmsolar farm6.4operational6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1057, -4.5353).