Blaenporth Solar Farm (7 MW)
Blaenporth Solar Farm is a 7 MW solar farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 3 September 2017; the record was last updated on 26 November 2019.
7 MWsolar farm
permission expiredstatus in REPD
26 November 2019record last updated
Ceredigioncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 May 2014 | Application submitted |
| 3 September 2014 | Planning permission granted |
| 3 September 2017 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 7 MW
- Status (REPD)
- permission expired
- Record last updated
- 26 November 2019
- Operator or applicant
- Juwi Renewable Energies
- Planning authority
- Ceredigion
- Planning application reference
- A140370
- Address (REPD)
- Blaenporth, Cardigan
- Council area (by location)
- Ceredigion
- Time to decision
- 15 weeks
- REPD reference
- 1327
Who decides
| Applications | Ceredigion | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 2 (11%) | 19% |
| Solar refused | 0 of 12 | 12% |
| Onshore wind refused | 2 of 7 | 45% |
| Median time from submission to decision | 35.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Llwyn Du Solar Farm | solar farm | 8 | operational | 0.9 |
| Crugmore Farm | solar farm | 6.4 | operational | 6.0 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1057, -4.5353).