Cefn Croes Wind Farm (58.5 MW)

Cefn Croes Wind Farm is a 58.5 MW wind farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 January 2005; the record was last updated on 22 April 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

58.5 MWwind farm
operationalstatus in REPD
22 April 2009record last updated
Ceredigioncouncil area

Planning timeline

DateStage
24 July 2000Application submitted
10 December 2001Planning permission granted
25 January 2005Operational

Project details

Technology
wind farm
Capacity
58.5 MW
Status (REPD)
operational
Record last updated
22 April 2009
Operator or applicant
Renewable Development Company Ltd, KENTECH Ltd
Planning authority
Ceredigion
Planning application reference
AD00737
Turbines
39
Address (REPD)
Canolbarth Forest, Devils Bridge Ceredigion
Council area (by location)
Ceredigion
Time to decision
72 weeks
REPD reference
2563

Who decides

ApplicationsCeredigionUK
Decided applications (solar, wind, battery)1910,236
Refused2 (11%)19%
Solar refused0 of 1212%
Onshore wind refused2 of 745%
Median time from submission to decision35.9 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bryn Duwind farm16.4operational3.2
Mynydd y Gwynt Wind Farmwind farm89.1refused on appeal5.1
Lluest y Gwynt Wind Farmwind farm50.4application submitted6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.405, -3.7507).