Cefn Croes Wind Farm (58.5 MW)
Cefn Croes Wind Farm is a 58.5 MW wind farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 January 2005; the record was last updated on 22 April 2009.
58.5 MWwind farm
operationalstatus in REPD
22 April 2009record last updated
Ceredigioncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 24 July 2000 | Application submitted |
| 10 December 2001 | Planning permission granted |
| 25 January 2005 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 58.5 MW
- Status (REPD)
- operational
- Record last updated
- 22 April 2009
- Operator or applicant
- Renewable Development Company Ltd, KENTECH Ltd
- Planning authority
- Ceredigion
- Planning application reference
- AD00737
- Turbines
- 39
- Address (REPD)
- Canolbarth Forest, Devils Bridge Ceredigion
- Council area (by location)
- Ceredigion
- Time to decision
- 72 weeks
- REPD reference
- 2563
Who decides
| Applications | Ceredigion | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 2 (11%) | 19% |
| Solar refused | 0 of 12 | 12% |
| Onshore wind refused | 2 of 7 | 45% |
| Median time from submission to decision | 35.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Bryn Du | wind farm | 16.4 | operational | 3.2 |
| Mynydd y Gwynt Wind Farm | wind farm | 89.1 | refused on appeal | 5.1 |
| Lluest y Gwynt Wind Farm | wind farm | 50.4 | application submitted | 6.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.405, -3.7507).