Mynydd Gorddu Wind Farm (10.2 MW)
Mynydd Gorddu Wind Farm is a 10.2 MW wind farm project in Ceredigion, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 April 1998; the record was last updated on 18 May 2006.
10.2 MWwind farm
operationalstatus in REPD
18 May 2006record last updated
Ceredigioncouncil area
Planning timeline
| Date | Stage |
|---|---|
| 4 January 1991 | Application submitted |
| 12 September 1991 | Planning permission granted |
| 18 April 1998 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 10.2 MW
- Status (REPD)
- operational
- Record last updated
- 18 May 2006
- Operator or applicant
- Cynllun Trydan Gwynt
- Planning authority
- Ceredigion
- Planning application reference
- not recorded
- Turbines
- 19
- Address (REPD)
- Mynydd Gorddu Elerch Tal-y-Bont Dyfed
- Council area (by location)
- Ceredigion
- Time to decision
- 36 weeks
- REPD reference
- 2559
Who decides
| Applications | Ceredigion | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 19 | 10,236 |
| Refused | 2 (11%) | 19% |
| Solar refused | 0 of 12 | 12% |
| Onshore wind refused | 2 of 7 | 45% |
| Median time from submission to decision | 35.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4663, -3.971).