Energy Projects Near You

Bryn Henllys (20 MW solar farm)

Bryn Henllys is a 20 MW solar farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 June 2018, not yet built; the record was last updated on 5 August 2020. REPD records the planning permission as expiring on 11 June 2021, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtmay be out of datestatus in REPD
5 August 2020record last updated
Powyscouncil area

REPD records the planning permission as expiring on 11 June 2021, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
6 February 2015Application submitted
11 June 2018Planning permission granted
11 June 2021Permission expired

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
5 August 2020
Operator or applicant
Lightsource BP
Planning authority
Powys
Planning application reference
P/2015/0176
Site area
45.2 ha
Address (REPD)
Land at Bryn Henllys Open Cast, Upper Cwmtwch, Cwmllynfell
Council area (by location)
Powys
Time to decision
174 weeks
Contracts for Difference
AR4
REPD reference
4775

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Varteg Hillwind farm12refused5.0
Land South of Ystalyferawind farm12refused5.0
Pencaerlan Solar Farmsolar farm25application submitted5.4
Hirfynyddwind farm18refused on appeal8.1
Mynydd Marchywel Wind Farmwind farm10refused on appeal8.4
Dulais Valleywind farm13.5refused8.9
Mynydd y Betwswind farm34.5operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7967, -3.7924).