Energy Projects Near You

Llethercynnon Farm Wind Farm (7.1 MW)

Llethercynnon Farm Wind Farm is a 7.1 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 22 January 2003; the record was last updated on 29 March 2005.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.1 MWwind farm
refusedstatus in REPD
29 March 2005record last updated
Powyscouncil area

Planning timeline

DateStage
18 April 2000Application submitted
22 January 2003Refused by the planning authority

Project details

Technology
wind farm
Capacity
7.1 MW
Status (REPD)
refused
Record last updated
29 March 2005
Operator or applicant
WINDJEN POWER LTD
Planning authority
Powys
Planning application reference
B/01/0111
Address (REPD)
Nr Garthbrengy, Powys
Council area (by location)
Powys
Time to decision
144 weeks
REPD reference
2632

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0152, -3.3813).