Neuadd Goch Bank Wind Farm (27 MW)
Neuadd Goch Bank Wind Farm is a 27 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: appeal withdrawn; the record was last updated on 26 March 2020.
27 MWwind farm
appeal withdrawnstatus in REPD
26 March 2020record last updated
Powyscouncil area
Planning timeline
| Date | Stage |
|---|---|
| 27 January 2012 | Application submitted |
| 22 April 2014 | Appeal lodged |
| 14 July 2014 | Refused by the planning authority |
| 1 March 2020 | Appeal withdrawn |
Project details
- Technology
- wind farm
- Capacity
- 27 MW
- Status (REPD)
- appeal withdrawn
- Record last updated
- 26 March 2020
- Operator or applicant
- RWE Npower Renewables
- Planning authority
- Powys
- Planning application reference
- P/2012/0040
- Appeal reference
- APP/T6850/A/14/2217488
- Turbines
- 9
- Address (REPD)
- Dolfor, Newtown Powys
- Council area (by location)
- Powys
- Time to decision
- 128 weeks
- REPD reference
- 4183
Who decides
| Applications | Powys | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 42 | 10,236 |
| Refused | 15 (36%) | 19% |
| Solar refused | 2 of 15 | 12% |
| Onshore wind refused | 12 of 24 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 78.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Llanbadarn Fynydd Wind Farm | wind farm | 51 | refused | 2.5 |
| Garn Fach Wind Farm | wind farm | 85 | approved, not built | 5.2 |
| Llandinam Windfarm Repowering and Extension | wind farm | 102 | approved, not built | 5.3 |
| Garreg Lwyd | wind farm | 34 | operational | 5.8 |
| Llandinam Windfarm | wind farm | 31 | operational | 5.8 |
| Bryngydfa Wind Farm | wind farm | 36 | application submitted | 5.9 |
| Fferm Wynt Llaithddu Cyf | wind farm | 66.7 | refused | 6.3 |
| Hirddywell Windfarm | wind farm | 14.8 | application withdrawn | 7.5 |
| Hirddywel | wind farm | 27 | application submitted | 8.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4491, -3.3453).