Fferm Wynt Llaithddu Cyf (66.7 MW wind farm)

Fferm Wynt Llaithddu Cyf is a 66.7 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 7 September 2015; the record was last updated on 14 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

66.7 MWwind farm
refusedstatus in REPD
14 September 2015record last updated
Powyscouncil area

Planning timeline

DateStage
7 May 2008Application submitted
7 September 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
66.7 MW
Status (REPD)
refused
Record last updated
14 September 2015
Operator or applicant
Fferm Wynt Llaithddu Cyf
Planning authority
Powys
Planning application reference
not recorded
Turbines
29
Address (REPD)
Llaithddu, Powys
Council area (by location)
Powys
Time to decision
383 weeks
REPD reference
3991

Who decides

ApplicationsPowysUK
Decided applications (solar, wind, battery)4210,236
Refused15 (36%)19%
Solar refused2 of 1512%
Onshore wind refused12 of 2445%
Battery storage refused1 of 316%
Median time from submission to decision78.6 weeks17.0 weeks
Appeals lodged / allowed5 / 3—

UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.

Other large projects within 10 km

ProjectTypeMWStatuskm
Garn Fach Wind Farmwind farm85approved, not built1.2
Hirddywell Windfarmwind farm14.8application withdrawn1.7
Hirddywelwind farm27application submitted3.0
Llandinam Windfarmwind farm31operational3.9
Llandinam Windfarm Repowering and Extensionwind farm102approved, not built4.2
Llanbadarn Fynydd Wind Farmwind farm51refused5.7
Neuadd Goch Bank Wind Farmwind farm27appeal withdrawn6.3
Garreg Lwydwind farm34operational8.6
Bryngydfa Wind Farmwind farm36application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4089, -3.4103).