Bryngydfa Wind Farm (36 MW)
Bryngydfa Wind Farm is a 36 MW wind farm project in Powys, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 3 April 2009, no decision recorded; the record was last updated on 16 September 2014. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.
The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.
Planning timeline
| Date | Stage |
|---|---|
| 3 April 2009 | Application submitted |
Project details
- Technology
- wind farm
- Capacity
- 36 MW
- Status (REPD)
- application submitted
- Record last updated
- 16 September 2014
- Operator or applicant
- Private Developer
- Planning authority
- Powys
- Planning application reference
- P/2009/0384
- Turbines
- 12
- Address (REPD)
- Felindre (Northern Area SO135809, South Knighton) Powys LD7 1Y
- Council area (by location)
- Powys
- REPD reference
- 4570
Who decides
| Applications | Powys | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 42 | 10,236 |
| Refused | 15 (36%) | 19% |
| Solar refused | 2 of 15 | 12% |
| Onshore wind refused | 12 of 24 | 45% |
| Battery storage refused | 1 of 3 | 16% |
| Median time from submission to decision | 78.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 5 / 3 | — |
UK: all UK planning authorities. Counted under these REPD planning authority names: DECC (S36), Powys.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Garreg Lwyd | wind farm | 34 | operational | 1.0 |
| Llanbadarn Fynydd Wind Farm | wind farm | 51 | refused | 4.1 |
| Neuadd Goch Bank Wind Farm | wind farm | 27 | appeal withdrawn | 5.9 |
| Garn Fach Wind Farm | wind farm | 85 | approved, not built | 8.3 |
| Fferm Wynt Llaithddu Cyf | wind farm | 66.7 | refused | 9.4 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4192, -3.2733).