Energy Projects Near You

Solar, wind and battery projects near Craven Arms (SY7)

4 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SY7 (Shropshire): 1 approved but not yet running, 2 operational. The largest live scheme is The Conery (1 MW wind turbine, approved on 20 June 2025, not yet built), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

4projects within 10 km
0awaiting a decision
1approved, not running
2operational

Projects within 10 km of SY7

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Henley Solar Farmsolar farmsolar farm6.5operationalupdated Dec 2017Nov 2014granted Jan 2016Dec 2017Shropshire8.8
Henley Solar Farmsolar farmsolar farm6.5refusedupdated Nov 2014Jul 2014refused Oct 2014Nov 2014Shropshire9.3
The Conerywind turbinewind turbine1approved, not builtupdated Jul 2025Jan 2025granted Jun 2025Jul 2025Shropshire9.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Bromfield Sand and Gravelsolar farmsolar farm0.5operationalupdated Oct 2019Feb 2015granted Jun 2015Oct 2019Shropshire9.3

Distance from the average position of the SY7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300210
Wind turbine101001

MW in pipeline: pending, approved and under-construction capacity.

How Shropshire decides solar, wind and battery applications

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

All projects in Shropshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.