Henley Solar Farm (6.5 MW, REPD 1997)

Henley Solar Farm is a 6.5 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 27 October 2014; the record was last updated on 6 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.5 MWsolar farm
refusedstatus in REPD
6 November 2014record last updated
Shropshirecouncil area

Planning timeline

DateStage
7 July 2014Application submitted
27 October 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
6.5 MW
Status (REPD)
refused
Record last updated
6 November 2014
Operator or applicant
Henley Solar Farm
Planning authority
Shropshire
Planning application reference
14/02807/FUL
Site area
22.2 ha
Address (REPD)
Land North of Henley Common, Henley Lane, Acton Scott, Church Stretton, Shropshire
Council area (by location)
Shropshire
Time to decision
16 weeks
REPD reference
1997

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Henley Solar Farmsolar farm6.5operational0.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.491, -2.8015).