Kingston Road, Slimbridge (36 MW battery storage)

Kingston Road, Slimbridge is a 36 MW battery storage project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 July 2024, not yet built; the record was last updated on 16 August 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWbattery storage
approved, not builtstatus in REPD
16 August 2024record last updated
Stroudcouncil area

Planning timeline

DateStage
4 September 2023Application submitted
17 July 2024Planning permission granted
17 July 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
36 MW
Status (REPD)
approved, not built
Record last updated
16 August 2024
Operator or applicant
Relay Slimbridge Limited
Planning authority
Stroud
Planning application reference
S.23/1593/FUL
Address (REPD)
Land North East Of Kingston Road Slimbridge
Council area (by location)
Stroud
Time to decision
45 weeks
Name in REPD
Kingston Road, Slimbridge - Battery Storage
REPD reference
14882

Earlier applications for this site

ApplicationMWSubmittedOutcome
Kingston Road, Slimbridge S.22/1157/FUL3613 June 2022replaced by a revised application

Who decides

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hillhouse Farmsolar farm28.5operational1.5
Awre Penisular Farmer's Community Solar Schemesolar farm49.9refused5.0
Solar Panels at Ne/O Poulton Court Farmsolar farm40application submitted5.2
Berkeley Valewind farm16refused5.4
Northington Lanebattery storage35approved, not built5.6
Land At Actrees Farmsolar farm5operational6.5
Land North of Actrees Solar Farmbattery storage49.9abandoned6.6
Solar PV Panels & Battery Storage Facilitybattery storage49.9application withdrawn6.9
Solar PV Panels & Battery Storage Facilitysolar farm49.9application withdrawn6.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7361, -2.3848).