Energy Projects Near You

Land At Actrees Farm (5 MW solar farm)

Land At Actrees Farm is a 5 MW solar farm project in Stroud, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 January 2016; the record was last updated on 4 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 March 2016record last updated
Stroudcouncil area

Planning timeline

DateStage
26 June 2015Application submitted
29 October 2015Planning permission granted
25 November 2015Construction started
28 January 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 March 2016
Operator or applicant
Actrees Solar Power/ Vogt Solar
Planning authority
Stroud
Planning application reference
S.15/1523/FUL
Address (REPD)
Land At Actrees Farm, Heathfield, Alkington, Berkeley
Council area (by location)
Stroud
Time to decision
18 weeks
Name in REPD
Land At Actrees Farm
REPD reference
5425

Recorded together with Land North of Actrees Solar Farm (49.9 MW battery storage, abandoned).

Who decides

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Berkeley Valewind farm16refused1.3
Upper Wick Solar Farmsolar farm5operational1.8
Hook Street Energy Storage Compoundbattery storage100refused3.8
Upper Huntingford Farmsolar farm7.7operational4.3
Woodlands Farm, Clapton - Ground Mounted Solar Parksolar farm36approved, not built4.8
Worlds End Solar Farmsolar farm49.9application submitted6.1
Kingston Road, Slimbridgebattery storage36approved, not built6.5
Hillhouse Farmsolar farm28.5operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6815, -2.4194).