Energy Projects Near You

Solar, wind and battery projects near Stonehouse (GL10)

30 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GL10 (Stroud): 1 is waiting for a planning decision, 16 approved but not yet running, 4 operational. The largest live scheme is Moreton Lane Solar Farm & Battery Storage (49.9 MW solar farm, approved on 5 April 2022, not yet built; REPD status may be out of date), 5.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30projects within 10 km
1awaiting a decision
16approved, not running
4operational

Projects within 10 km of GL10

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Delphi Diesel Systems, Brunel Wayrooftop solarrooftop solar1.6approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024Stroud1.1
Fawkes 1solar farmsolar farm4.7refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015Stroud1.4
Fawkes 2 Solar Farmsolar farmsolar farm4.7refusedupdated Dec 2015Jul 2015refused Nov 2015Dec 2015Stroud1.5
Windmill Hillwind farmwind farm1.5refusedupdated Feb 2004Oct 2000refused May 2001Feb 2004Stroud5.0
Lynch Knoll Wind Farm (Extension)wind farmwind farm1.5appeal withdrawnupdated Jan 2010Oct 2000refused Dec 2000Jan 2010Stroud5.0
Hillhouse Farmsolar farmsolar farm28.5operationalupdated Apr 2015Aug 2014granted Dec 2014Apr 2015Stroud5.2
Land at Box Roadsolar farmsolar farm2.2operationalupdated Jun 2016Jun 2015granted Sep 2015Jun 2016Stroud5.8
Moreton Lane Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022Stroud5.8
Moreton Lane Solar Farm & Battery Storagebattery storagebattery storage49.9approved, not built may be out of dateupdated Apr 2022Feb 2021granted Apr 2022Apr 2022Stroud5.8
Kingston Road, Slimbridgebattery storagebattery storage36approved, not builtupdated Aug 2024Sep 2023granted Jul 2024Aug 2024Stroud6.7
Epney, Framilode Solar Farm & Battery Storagesolar farmsolar farm49.5refusedupdated Dec 2025Jun 2025refused Dec 2025Dec 2025Stroud7.1
Unit Q1, Quadrant Distribution Centre, Hardwickrooftop solarrooftop solar1approved, not builtupdated May 2022Apr 2022granted May 2022May 2022Stroud7.4
High Green Longney Estate Solar Farmsolar farmsolar farm25permission expiredupdated Sep 2020Mar 2018granted Sep 2019Sep 2020Stroud7.5
High Green Longney Estate Solar Farmsolar farmsolar farm20permission expiredupdated Jul 2022Apr 2019granted Jul 2019Jul 2022Stroud7.5
Brookthorpe Solar Farmsolar farmsolar farm8approved, not builtupdated Feb 2026Apr 2024granted Dec 2024Feb 2026Stroud9.4
Awre Penisular Farmer's Community Solar Schemesolar farmsolar farm49.9refusedupdated Dec 2017Jun 2015refused Jan 2016Dec 2017Forest of Dean9.8
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
A B B Limited, Oldends Lanesolar farmsolar farm0.8approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Stroud0.7
Brunel Wayrooftop solarrooftop solar0.5approved, not built may be out of dateupdated Mar 2022Feb 2022granted Apr 2022Mar 2022Stroud1.1
Renishaw PLC Factoryrooftop solarrooftop solar0.8operationalupdated May 2020Jun 2018granted Mar 2019May 2020Stroud1.1
Sainsburys Supermarket, Dudbridge Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated Aug 2024Aug 2024—Aug 2024Stroud3.3
Science building, Dudbridge Roadrooftop solarrooftop solar0.6approved, not builtupdated Apr 2023Feb 2023granted Mar 2023Apr 2023Stroud3.7
Dobbies Garden Centres, Bath Roadrooftop solarrooftop solar0.2application withdrawnupdated Dec 2023Oct 2023—Dec 2023Stroud5.2
Wellington House, Bath Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Dec 2021granted Jan 2022Dec 2021Stroud6.0
Shipton Mill Limited, Frampton On Severn Industrial Parkrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Stroud6.4
MG Markey Group, Quadrant Wayrooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Stroud7.4
Francis And Lewis International, Waterwells Driverooftop solarrooftop solar0.2approved, not builtupdated Dec 2022Aug 2022granted Nov 2022Dec 2022Gloucester7.7
Alpha Colour Printers, Waterwells Driverooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Gloucester7.7
Rednock Schoolrooftop solarrooftop solar0.2under constructionupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Stroud8.1
Mobile Telephone Exchange (MTX)rooftop solarrooftop solar—operationalupdated Apr 2023Dec 2022—Apr 2023Gloucester9.8
Arlingham House, Quedgeleyrooftop solarrooftop solar0.3approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021Gloucester9.8

Distance from the average position of the GL10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm11032458.7
Rooftop solar15111205.4
Wind farm200010
Battery storage2020085.9

MW in pipeline: pending, approved and under-construction capacity.

How Stroud decides solar, wind and battery applications

ApplicationsStroudUK
Decided applications (solar, wind, battery)3410,236
Refused8 (24%)19%
Solar refused4 of 2512%
Onshore wind refused3 of 445%
Battery storage refused1 of 516%
Median time from submission to decision17.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Stroud

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GL10, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.